Real C_TPLM22_64 SAP Networks Exam Question Samples For Free

TestActual is providing C_TPLM22_64 exam preparation material for SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam for last 10 years and has gathered more then 50,000+ satisfied customers around the world. Our success rate for Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam is remarkable. You may try the free demo of our Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam dumps material, before purchase. We provide you latest C_TPLM22_64 exam questions. The candidates will also be entitled 90 days free updates.

♥ VALID C_TPLM22_64 Exam Questions 2018 ♥

C_TPLM22_64 exam questions, C_TPLM22_64 PDF dumps; C_TPLM22_64 exam dumps:: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html (100 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest SAP C_TPLM22_64 Dumps Exam Questions and Answers:

Version: 5.0
Question: 21

Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.
What is the status that must be set before you can enter actual start and actual end dates?
There are 2 correct answers to this question.
Response:

A. Partially released
B. Released
C. Partially set
D. Partially finished

Answer: AB

Question: 22

In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?
There are 2 correct answers to this question.
Response:

A. Project view
B. Resource view
C. Work center view
D. Assignment view

Answer: AC

Question: 23

What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:

A. Cost centers
B. Cost elements
C. Profit centers
D. Profit center hierarchy

Answer: CD

Question: 24

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:

A. Contractual management
B. Claim management
C. Claim Planning
D. Variance management

Answer: B

Question: 25

Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:

A. Functional areas
B. Residence times
C. Classification indicator
D. Functional areas

Answer: B

Question: 26

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:

A. Billing element
B. Cost element
C. Pricing element
D. Account assignment element

Answer: AD